Ponce de Leon Resurfacing
We received the following notice late last week from our friends at the Georgia Department of Transportation.
Resurfacing of Ponce de Leon Avenue has commenced.
The work schedule (weather permitting) is from 7 p.m. to 5 a.m. Sundays through Thursdays (no Friday/Saturday work). The entire resurfacing should be completed within four weeks.
Workers will start in the eastbound direction, closing only one lane at a time; they will then turn and work westbound, again closing one lane at a time. The work will be completed in three sections:
Section 1 — North Avenue from State Street to Tech Parkway; approximate time one night.
Section 2 — North Avenue from Spring Street to Piedmont Avenue and Piedmont Avenue to Ponce de Leon Avenue; approximate time, four to five nights.
Section 3 — Ponce de Leon Avenue from Piedmont Avenue to Moreland Avenue/Briarcliff Road; approximate time, 10 to 12 nights.
For more information on Georgia Department of Transportation projects, please visit the GDOT website: www.dot.ga.gov — this project identification (PI) number is M004536.